The Party Wall Act Explained: Your Rights and Responsibilities

By Twickenham Surveyors | January 2025 | 15 min read

Party wall surveying between adjoining properties in West London

If you're planning building works in Twickenham, Richmond, or anywhere in West London that affect a wall shared with your neighbour, you need to understand the Party Wall etc. Act 1996. At Twickenham Surveyors, we act as party wall surveyors for hundreds of cases every year, helping both building owners and adjoining owners navigate this important legislation.

The Party Wall Act exists to prevent and resolve disputes between neighbours when building works affect shared walls, boundaries, or nearby structures. While it may seem like additional bureaucracy, following the correct procedure protects both you and your neighbours, provides a clear legal framework, and can actually prevent costly disputes and delays.

What is the Party Wall Act?

The Party Wall etc. Act 1996 is legislation that applies to England and Wales (Scotland has different provisions). It provides a framework for preventing and resolving disputes in relation to party walls, boundary walls, and excavations near neighbouring buildings.

Key Purposes of the Act

Importantly, the Act is separate from planning permission or building regulations - you may need all three for major works.

When Does the Party Wall Act Apply?

You need to follow Party Wall Act procedures if your proposed works fall into any of these categories:

1. Work on an Existing Party Wall (Section 2)

A party wall is a wall that stands on the boundary between two properties and is shared by both owners. Works requiring a party wall notice include:

Common examples in Twickenham and Richmond terraces:

2. Building a New Wall on the Boundary Line (Section 1)

If you're building a new wall right on the boundary line between properties:

Note: If the wall is entirely on your land (even 50mm away from the boundary), Party Wall Act doesn't apply, though you should still inform neighbours as a courtesy.

3. Excavation Within 3 or 6 Meters of a Neighbouring Building (Section 6)

This is particularly relevant for basement conversions and extensions in West London:

Within 3 meters:

Within 6 meters:

Works That DON'T Require Party Wall Notice

These common works generally don't trigger the Act:

The Party Wall Process: Step by Step

Step 1: Determine if the Act Applies (2-3 months before starting work)

Step 2: Serve Party Wall Notice (At least 2 months before for wall works, 1 month for excavations)

The building owner must serve written notice on all affected adjoining owners:

Notice must include:

Who to serve notice on:

Timing requirements:

Step 3: Neighbour Responds (14 days to respond)

The adjoining owner has three options:

Option 1: Consent to the Works

If your neighbour agrees in writing, you can proceed without appointing surveyors. However, this is relatively rare because:

Most neighbours are advised to either dissent or not respond, triggering the surveyor appointment process which protects their interests.

Option 2: Dissent (Disagree with the Notice)

Dissenting doesn't mean you object to the works - it means you want the formal surveyor process to protect your interests. This is the most common and sensible response.

Option 3: No Response (Deemed Dissent)

If the neighbour doesn't respond within 14 days, they're deemed to have dissented, and the surveyor process automatically applies.

Step 4: Appoint Party Wall Surveyors

There are two options for surveyor appointments:

Option A: Agreed Surveyor (Single Surveyor)

Both parties agree to appoint the same surveyor who acts impartially for both sides:

Option B: Two Surveyors (Plus Third Surveyor if needed)

Each party appoints their own surveyor, who then work together:

Advantages: Each party has dedicated representation, appropriate for complex works or disputed matters

Typical costs: £1,000-£3,000+ per side (building owner usually pays both sets of reasonable fees)

Step 5: Pre-Works Schedule of Condition

The appointed surveyor(s) will:

This is crucial evidence if any damage claims arise later.

Step 6: Party Wall Award

The surveyor(s) will prepare and serve a Party Wall Award, which is a legal document setting out:

The Award is legally binding on both parties and remains with the property if it's sold.

Step 7: Works Proceed

Step 8: Post-Works Inspection

After completion:

Rights and Responsibilities

Building Owner's Rights

As the person carrying out works, you have the right to:

Building Owner's Responsibilities

Adjoining Owner's Rights

As the neighbour affected by works, you have the right to:

Adjoining Owner's Responsibilities

Costs: Who Pays What?

Building Owner Pays For

Typical Cost Breakdown for Building Owner

Simple single-story rear extension (one neighbour, agreed surveyor):

Loft conversion affecting two neighbours (two surveyors each side):

Large basement conversion (multiple neighbours, complex works):

When Costs Are Shared

In certain circumstances, costs may be shared between building owner and adjoining owner:

Common Disputes and How to Avoid Them

1. "My Neighbour Won't Respond to the Notice"

Solution: If no response within 14 days, they're deemed to have dissented. You can then appoint a surveyor on their behalf and proceed.

2. "My Neighbour is Refusing Access"

Solution: The Award can require reasonable access. If they still refuse, this is contempt of the Award and you can seek legal enforcement.

3. "The Works Have Caused Damage"

Solution: This is why the schedule of condition is crucial. The building owner must make good damage caused by the works. Disputes about causation are resolved by the surveyor(s).

4. "My Neighbour Says I Need a Party Wall Notice But I Don't Think So"

Solution: Get advice from a qualified party wall surveyor. It's better to serve notice if in doubt - failure to serve when required can result in injunctions stopping works and legal costs.

5. "The Surveyor's Fees Seem Excessive"

Solution: Fees must be "reasonable." If you think they're excessive, you can challenge them. The Award should detail fees or state they'll be determined later. Get your own surveyor's opinion on reasonableness.

Penalties for Not Following the Party Wall Act

If you proceed with notifiable works without following the Act, you risk:

Real example: A Richmond homeowner started a loft conversion without serving party wall notice. The neighbour obtained an injunction, stopping works for 4 months while the party wall process was completed retrospectively. Total additional costs: £15,000 in legal fees, surveyor costs, contractor delays, and storage for displaced possessions.

Party Wall Act and Common Scenarios

Loft Conversions

Most loft conversions in terraced properties trigger the Act:

Timeline: Serve notice 2 months before starting. Process typically takes 6-10 weeks total.

Rear Extensions

Single or double-story rear extensions commonly require notices for:

Tip: Design extensions to avoid cutting into party walls if possible - this can reduce costs and complexity.

Basement Conversions

Almost always trigger Section 6 (excavation notices):

Costs: Party wall costs for basement conversions can be £5,000-£15,000 due to multiple neighbours and complexity.

Removing Chimney Breasts

Requires notice if the chimney is built into or forms part of the party wall:

Choosing a Party Wall Surveyor

Essential Qualifications

Questions to Ask

Why Choose Twickenham Surveyors

Frequently Asked Questions

Can my neighbour stop my building works?

No. If you follow the Party Wall Act correctly and obtain an Award, your neighbour cannot prevent the works proceeding. They can disagree with the notice (which triggers the surveyor process) but cannot ultimately block legitimate works.

What if my neighbour won't appoint a surveyor?

If they don't appoint a surveyor within 10 days of dissenting (or being deemed to dissent), your surveyor can appoint one on their behalf. The process continues regardless.

Do I need party wall notice for planning-exempt works?

Yes, potentially. Party Wall Act is completely separate from planning permission. Even if your works are permitted development, you still need to follow the Act if the works fall within its scope.

What if I've already started works without serving notice?

Stop immediately and serve notice. You'll likely need a retrospective Award. Continuing risks an injunction. Consult a party wall surveyor urgently.

How long does the party wall process take?

Minimum 2 months for wall works (notice period) but typically 3-4 months total to allow for surveyor appointments, schedules, and Award preparation. Plan ahead!

Can I serve party wall notice myself, or do I need a surveyor?

You can serve notice yourself - templates are available online. However, many building owners use surveyors to ensure notices are correct and to avoid mistakes that could cause delays.

What happens if there's a dispute between the two surveyors?

The two surveyors must try to reach agreement. If they can't, they appoint a third surveyor who makes the final decision. The third surveyor's determination is binding.

Need Party Wall Advice or Surveyor Services?

Expert RICS party wall surveyors serving West London

500+

Party Wall Cases

4-6 Weeks

Typical Award Time

RICS

Qualified Experts

Get Expert Advice Today

About the Author

Twickenham Surveyors are RICS qualified party wall surveyors with extensive experience across West London. We've successfully completed hundreds of party wall cases in Twickenham, Richmond, Kingston, and surrounding areas, acting for both building owners and adjoining owners. Our team provides clear, professional advice and ensures the party wall process runs smoothly, protecting the interests of all parties while allowing legitimate building works to proceed without unnecessary delays. Contact us for expert party wall advice and surveyor services.

← Back to Blog